Is the timesheet managers in Project Server 2013?

Is the timesheet managers in Project Server 2013?

I searched but everything I tried, failed (such as this solution) : http://blog.cps.co.uk/2013/07/29/timesheet-managers-in-project-server-2013/ ” The Timesheet Managers is of course populated, the user who has the automatic approval is not a timesheet manager.

When to use CSOM in Project Server 2013?

Apps and the security model Apps must use the CSOM for CRUD (create, read, update, delete) operations with Project Server 2013 and Project Online. Project apps do not use the app-only authentication model in SharePoint 2013. A Project Server app requires a specific permission request scope that specifies on whose behalf commands are being run.

Is the Project Server CSOM compatible with Silverlight?

The Project Server CSOM includes a Microsoft .NET CSOM, a Microsoft Silverlight CSOM, a Windows Phone 8 CSOM, and a JavaScript object model (JSOM). In addition, the CSOM includes an OData service that enables a REST interface.

Which is client side object model for Project Server 2013?

The Project Server 2013 client-side object model (CSOM) implements common server functionality. The Project Server CSOM includes a Microsoft .NET CSOM, a Microsoft Silverlight CSOM, a Windows Phone 8 CSOM, and a JavaScript object model (JSOM).

How to get approval from a timesheet manager?

I would like an approval from a Timesheet Manager but when an user turn it in final timesheet, the timesheet is automatically approved by the system. I searched but everything I tried, failed (such as this solution) : http://blog.cps.co.uk/2013/07/29/timesheet-managers-in-project-server-2013/ ”

How to set up time and task progress approval?

Only those people listed on the Timesheet Managers page can approve timesheets. Choose Settings > PWA Settings. Under Time and Task Management, choose Timesheet Managers. Choose Managers > Add Manager. Choose the person you want to add as an approver, and then choose OK.

How to add approvals in project web app?

In Project Web App, in the left navigation, click Approvals. On the ribbon, click Workflow Approvals. On the Workflow Tasks list, click All Tasks. Click Customize approval options. On the ribbon, click Edit.