How do I change the default duration in MS Project?

How do I change the default duration in MS Project?

In Project, the default time unit for work is hours, but you can change it to be minutes, days, weeks, or months:

  1. Choose File > Options.
  2. In the Project Options dialog box, choose Schedule.
  3. In the Work is entered in list, choose the time unit that you want.

Can MS Project calculate duration?

Description The Duration field is the total span of active working time for a task. This is generally the amount of working time from the start to the finish of a task. How Calculated Project calculates the duration of a task by counting the amount of active working time between the scheduled start and end of the task.

How do I remove duration in MS project?

Click the File tab and then click the Options button in the Backstage. In the Project Options dialog, click the Schedule tab. In the Scheduling options for this project section of the dialog, deselect the Show that scheduled tasks have estimated durations checkbox.

How to calculate the duration of a project?

Microsoft Project certainly seems to nudge a project manager into typing his or her task’s Duration into the project. Fortunately, you can just as easily type in Work and then have Project calculate the Duration based on the number of people you assign and their availability. The first step in using Project this way is to add the Work column.

How to set a task to fixed duration?

You probably want to set your task to “Fixed Duration” mode (double click on the task -> Advanced -> Task Type). You can also set “Fixed Duration” as the default mode for tasks in Options menu. Resources is 100% if you assign one guy. So whatever you touch, MS-Project will adjust the other values to make the equation consistent.

What was the problem with MS Project 2010?

MS Project 2010 tries to be smart and tries to figure out correct dates and times. Unsurprisingly, it fails miserably once scheduling becomes just a little unusual. So now I have the following problem: When I set the end date right, MS Project changes the time it takes to something wrong.

What happens when I set the end date wrong in MS Project?

When I set the end date right, MS Project changes the time it takes to something wrong. When I set the time it takes right, MS Project changes the end date to something wrong. Every time I set one of them to the actual correct value the other is set to a wrong value. What can I do?