What is a product oriented WBS?

What is a product oriented WBS?

A deliverable-oriented WBS (also known as product-oriented WBS) decomposes the project scope into smaller and more manageable deliverables. Example of ultimate project deliverables in a construction project may include concrete structures, structural steels, building facade, and a building’s mechanical system.

What is verb oriented WBS?

Verb-oriented WBS: a task-oriented WBS defines the deliverable of project work in terms of the actions that must be done to produce the deliverable. It breaks the project into major phases instead of tasks. In this type, a “rolling wave” approach is adopted and only the near-term phase is planned in detail.

What is the difference between a deliverable oriented WBS and a process oriented WBS?

A process- centered WBS is similar to the deliverable- oriented WBS except that it is organized, the highest level of the hierarchy of the work breakdown structure. The process- centered WBS is organized by phases in a process rather than the deliverables as the deliverable- oriented WBS.

What should a WBS include?

The most helpful WBS plans contain these components:

  • Identification of which organization, department, or individual is responsible for each specific work piece.
  • The scheduled start and end dates.
  • Required resources.
  • Estimated cost of the project.
  • Charge numbers.
  • Contract details, requirements, and milestones.

What are the 2 types of WBS?

There are two types of work breakdown structures commonly employed in project management: the process-oriented WBS and deliverable-oriented WBS.

What is a Level 1 WBS?

At WBS Level 1 it shows 100 units of work as the total scope of a project to design and build a custom bicycle. At WBS Level 2, the 100 units are divided into seven elements. The number of units allocated to each element of work can be based on effort or cost; it is not an estimate of task duration.

How does a WBS work?

Work breakdown structure (WBS) in project management is a method for completing a complex, multi-step project. Breaking it down into smaller chunks means work can be done simultaneously by different team members, leading to better team productivity and easier project management.

What’s the meaning of ” action-oriented ” WBS?

Could you please explain what is meant by “action-oriented” details in the following sentence. Please provide an example. If the work breakdown structure designer attempts to capture any action-oriented details in the WBS, the designer will likely include either too many actions or too few actions.

Why do we need a process oriented WBSS?

Developing both deliverable-oriented and a process-oriented WBSs also helps project teams to better identify project activities. To learn more about project work breakdown structures and the way project management professionals can use the full potential of work breakdown structures, please contact us. [1].

What are the two main types of WBS?

The Two Main Types of Project Work Breakdown Structures (WBS) A process-oriented WBS, on the other hand, defines the project scope of work in terms of process steps (i.e., work phases, or functions) [5]. A process-oriented WBS defines what process steps need to be taken to deliver each of the project deliverables.

What is ” action-oriented ” work breakdown structure?

If the work breakdown structure designer attempts to capture any action-oriented details in the WBS, the designer will likely include either too many actions or too few actions. In the context of the rest of the section, it is saying that you should focus on the outcome desired, not the action needed to get there.